Oniru, Lagos

2026

Private Development

Bio-Digesters

Four Bio-Digesters, Abisogun Street, Oniru

Design and construction of four brick-built bio-digesters for a private development on Abisogun Street, Oniru, Lagos. Each unit was built in a deep excavation with multiple treatment chambers, rendered walls, and inlet, outlet and vent pipework. The work was completed despite a high water table in the excavation and tight supply of materials on site, and the lessons from this build now shape how VIKTROTECH plans every bio-digester project.

Challenge

The excavation sat below a high water level, so water kept collecting in the pits and had to be cleared before brickwork could continue. The build also had to keep moving with a limited site workforce and tight supplies of bricks, rods and cement.

Solution

Our engineer coordinated the crew and equipment on site, kept the excavation clear of water as each chamber went up, and staged the construction unit by unit so finished chambers were not held up by the others. Materials were re-ordered to the quantities set out in the quotation to keep work continuous.

Outcome

All four bio-digesters were completed and handed over. The project shaped our standard practice for future builds: a pumping machine on standby wherever the water table is high, materials purchased in full to the quoted quantities before work starts, a fixed mix ratio for every stage of construction, and a fully staffed site from day one.

Project Scope

01

Site excavation and setting out for four units

02

Brick-built multi-chamber digester construction

03

Internal rendering of chambers and partition walls

04

Inlet, outlet and vent pipework

05

Cover slabs and final backfilling

From the Site

Four Bio-Digesters, Abisogun Street, Oniru: site media 1